İzmit Bay South Approach Viaduct & Suspension Bridge – Turkey

Project Name Superstructure Erection Works for Gebze-İzmir Motorway South Approach Bridge of Suspension Bridge Project / Turkey
Country of Work Turkey
Client Nurol Construction & Trade Co. Inc
Type of Contract Subcontractor
Date of Contract 16.11.2013
Work Completion Date May 2015
Work Details
  • Project covers the design of a 1376 m long south approach bridge design and rection works of the suspension bridge connecting Yalova to Gebze as part of the bursa-İzmir Motorway BOT Project
  • Coordination for Bridge Design works and Superstrcture Erection Works will be carried out
  • Total superstructure weight is around 25000 tons. Launching of the superstructure and heavy lifting method by strand lifters will be implemented